Serge and Nat did some work on the boat this 4th of July before heading out to dinner and fireworks fun. We are steadily going down the list of ToDos

Achieved

  • Installed new LED bow light
    Photo
    Photo_2
  • Changed the nav lights switch in the instrument panel (bug finding led to the culprit)
    Img_20120704_155647
  • Removed a defective wire in the GPS circuit (bug finding led to the culprit) so all electrical instruments are now working again, including all lights (cabin, compass and both sets of navigation lights) - took a little while to debug all this.
  • Img_20120704_163151
  • Epoxied holes in deck core + wooden parts of the hatch rail
    Img_20120704_152253
  • Finished Elise's Boombox and worked to the 
    music of Nat's iPod
    Img_20120704_144231
  • Tested masthead tricolor navigation lights (worked like a charm)
    Img_20120704_142806
  • Made tag lines for both jib and spinnaker halyards
  • Tidied up some cables that were still hanging loose with cable clamps
  • Installed holders for flash lights so they are easy to find and access, yet out of the way